CLASSROOM ADDITIONS

 

MAP OF CLASSROOM ADDITIONS

Classroom Additions

  • Year Built: 1965

 

  • Number of Additional Classrooms: 18

 

  • Additional Scope of Work: Playground and parking modifications.

 

  • Completion: January 2018
Construction Video
  • Year Built: 1997

 

  • Number of Additional Classrooms: 22

 

  • Additional Scope of Work: Playground, parking modifications, HVAC component upgrades, fire alarm replacement, instructional walls, clock/intercom system upgrade, Local Area Network (LAN) upgrade, roof replacement

 

  • Project Status: In Construction

 

  • Estimated Completion Date: 2019-2020 School Year

 

Public Input Meetings

 

Tuesday, January 30, 2018
6 PM

 

John W. Bonner Elementary School – Multi-Purpose Room
765 Crestdale Lane
Las Vegas, NV 89144

 

Click here for postcard invitation.

 

Construction Video
  • Year Built: 1998

 

  • Number of Additional Classrooms: 22

 

  • Additional Scope of Work: Playground, parking modifications, HVAC component upgrades, fire alarm replacement, instructional walls, clock/intercom system upgrade, Local Area Network (LAN) upgrade, roof replacement

 

  • Completion: Fall 2018
Construction Video
  • Year Built: 1952

 

  • Number of Additional Classrooms: 22

 

  • Additional Scope of Work: Playground, parking modifications

 

  • Completion: Fall 2018
Construction Video
  • Year Built: 1963

 

  • Number of Additional Classrooms: 18

 

  • Additional Scope of Work: Playground, parking modifications

 

  • Completion: January 2018
Construction Video
  • Year Built: 1989

 

  • Number of Additional Classrooms: 18

 

  • Additional Scope of Work: Playground, parking modifications, instructional walls, Local Area Network (LAN) upgrade, roof replacement

 

  • Completion: Fall 2018

 

 

Public Input Meetings

 

Thursday, September 21, 2017
6:00 PM

 

Cynthia Cunningham Elementary School – Multi-Purpose Room
4145 Jimmy Durante Boulevard
Las Vegas, NV 89122

 

Click here for postcard invitation.

Construction Video
  • Year Built: 1963

 

  • Number of Additional Classrooms: 18

 

  • Additional Scope of Work: Playground, parking modifications, Instructional walls, Local Area Network (LAN) upgrade, Fire alarm replacement

 

  • Completion: Fall 2018
Construction Video
  • Year Built: 1999

 

  • Number of Additional Classrooms: 18

 

  • Additional Scope of Work: Playground, parking modifications, HVAC component upgrades, instructional walls, clock/intercom system upgrade, Local Area Network (LAN) upgrade, roof replacement

 

  • Completion: Fall 2018

 

 

Public Input Meetings

 

Wednesday, October 11, 2017
6:00 PM

Ollie Detwiler Elementary School – Multi-purpose Room
1960 Ferrell Street
Las Vegas, NV 89106

Click here for postcard invitation.

Construction Video
  • Year Built: 1976

 

  • Number of Additional Classrooms: 14

 

  • Additional Scope of Work: New multi-purpose room, conversion of old multi-purpose room space, playground, parking modifications, HVAC component upgrades, instructional walls, clock/intercom system upgrade, Local Area Network (LAN) upgrade

 

  • Completion: Fall 2018
Construction Video
  • Year Built: 1998

 

  • Number of Additional Classrooms: 18

 

  • Additional Scope of Work: Playground and parking modifications, replace cooling tower, boiler, chiller, HVAC controls, fire alarm, clock/intercom

 

  • Estimated Completion Date: January 2020

 

Public Input Meetings

 

Monday, September 25, 2017
6:00 PM

 

Raul P. Elizondo Elementary School – Multi-Purpose Room
4865 Goldfield Street
North Las Vegas, NV 89031

 

Click here for postcard invitation.

  • Year Built: 1991

 

  • Number of Additional Classrooms: 18

 

  • Additional Scope of Work: Playground, parking modifications

 

  • Completion: Fall 2018

 

Public Input Meetings

Monday, October 16, 2017
6:00 PM

Wing and Lilly Fong Elementary School – Multi-purpose Room
2200 James Bilbray Drive
Las Vegas, NV 89108

Click here for postcard invitation.

Construction Video
  • Year Built: 1997

 

  • Number of Additional Classrooms: 18

 

  • Additional Scope of Work: Playground and parking modifications, replace chiller, HVAC (Heating, Ventilation, Air Conditioning) controls, HVAC Rooftop Units, Fire Alarm, Clock/Intercom, LAN Upgrade, Instructional Walls, Replace Roof

 

  • Project Status: In Construction

 

  • Estimated Completion Date: 2019-2020 School Year
Construction Video
  • Year Built: 1991

 

  • Number of Additional Classrooms: 18

 

  • Additional Scope of Work: Playground, parking modifications, replace clock/intercom system, replace roof

 

  • Project Status: In Construction

 

  • Estimated Completion Date: 2019-2020 School Year
Construction Video
  • Year Built: 1962

 

  • Number of Additional Classrooms: 18

 

  • Additional Scope of Work: Playground, parking modifications

 

  • Completion: Fall 2018
construction video
  • Year Built: 1993

 

  • Number of Additional Classrooms: 22

 

  • Additional Scope of Work: Playground, parking modifications

 

  • Completion: Fall 2018
construction video
  • Year Built: 2000

 

  • Number of Additional Classrooms: 22

 

  • Additional Scope of Work: Playground, parking modifications, fire and intrusion alarm replacements, security cameras replacement, HVAC component upgrades, instructional walls, Local Area Network (LAN) upgrade, roof replacement

 

  • Completion: Fall 2018
construction video
  • Year Built: 1989

 

  • Number of Additional Classrooms: 18

 

  • Additional Scope of Work: Playground and parking modifications, replace security cameras, clock/intercom, LAN (Local Area Network) upgrade, instructional walls, replace roof

 

  • Completion: Fall 2018
Construction Video
  • Year Built: 1987

 

  • Number of Additional Classrooms: 18

 

  • Additional Scope of Work: Playground, parking modifications

 

  • Completion: Fall 2018

 

 

Public Input Meetings

 

Wednesday, August 23, 2017
6:00 PM
Doris M. Reed Elementary School – Multi-Purpose Room
2501 Winwood Street
Las Vegas, NV 89108

 

Click here for postcard invitation.

construction video
  • Year Built: 1965

 

  • Number of Additional Classrooms: 18

 

  • Additional Scope of Work: Playground, parking modifications, fire sprinkler system replacement

 

  • Completion: January 2018
Construction Video
  • Year Built: 1958

 

  • Number of Additional Classrooms: 18

 

  • Additional Scope of Work: Playground, parking modifications, HVAC component upgrades, instructional walls, Local Area Network (LAN) upgrade

 

  • Completion: Fall 2018

 

 

Public Input Meetings

 

Tuesday, September 19, 2017
6:00 PM

 

C.P. Squires Elementary School – Multi-Purpose Room

1312 East Tonopah Avenue
North Las Vegas, NV 89030

 

Click here for postcard invitation.

Construction Video
  • Year Built: 1990

 

  • Number of Additional Classrooms: 22

 

  • Additional Scope of Work: Playground, parking modifications

 

  • Completion: Fall 2018
construction video
  • Year Built: 1959

 

  • Number of Additional Classrooms: 18

 

  • Additional Scope of Work: Playground, parking modifications

 

  • Completion: Fall 2018

 

 

Public Input Meetings

 

Tuesday, August 29, 2017
6:00 PM

 

Vegas Verdes Elementary School – Multi-Purpose Room
4000 El Parque Avenue
Las Vegas, NV 89102

 

Click here for postcard invitation.

construction video
  • Year Built: 1963

 

  • Number of Additional Classrooms: 18

 

  • Additional Scope of Work: Playground, parking modifications

 

  • Completion: Fall 2018
Construction Video
  • Year Built: 1977

 

  • Number of Additional Classrooms: 22

 

  • Additional Scope of Work: Playground, parking modifications, fire alarm replacement, instructional walls, clock/intercom system upgrade, Local Area Network (LAN) upgrade

 

  • Project Status: In Construction

 

  • Estimated Completion Date: 2018-2019 School Year

 

  • Completion: Fall 2018
construction video
  • Year Built: 1959

 

  • Number of Additional Classrooms: 18

 

  • Additional Scope of Work: Playground, parking modifications, fire alarm replacement, clock/intercom system upgrade

 

  • Completion: Fall 2018

 

Public Input Meetings

 

Wednesday, November 1, 2017
6:00 PM

 

Halle Hewetson Elementary School – Multi-Purpose Room
701 North 20th Street
Las Vegas, NV 89101

 

Click here for postcard invitation.

Construction Video
  • Year Built: 2002

 

  • Number of Additional Classrooms: 18

 

  • Additional Scope of Work: To be determined

 

  • Estimated Completion Date: 2020-2021 School Year

 

Public Input Meetings

 

Tuesday, January 22, 2019
6:00 PM

 

Tony Alamo Elementary School – Multi-Purpose Room
7455 El Camino Road
Las Vegas, NV 89139

 

Click here for postcard invitation.

  • Year Built: 1987

 

  • Number of Additional Classrooms: 22

 

  • Additional Scope of Work: Playground, parking modifications, Instructional walls, Local Area Network (LAN) upgrade

 

  • Completion: Fall 2018
Construction Video
  • Year Built: 1965

 

  • Number of Additional Classrooms: 18

 

  • Additional Scope of Work: Playground, parking modifications

 

  • Completion: January 2018

 

  • Year Built: 1990

 

  • Number of Additional Classrooms: 18

 

  • Additional Scope of Work: Playground, parking modifications, provide bus loop, roof replacement

 

  • Completion: January 2018
Construction Video
  • Year Built: 1991

 

  • Number of Additional Classrooms: 14

 

  • Additional Scope of Work: Playground, parking modifications, clock/intercom system upgrade

 

  • Completion: Fall 2018
Construction Video
    • Year Built: 1997

 

    • Number of Additional Classrooms: 14

     

    • Additional Scope of Work: Playground and parking modifications, replace cooling tower, HVAC controls, fire alarm, clock/intercom, Local Area Network (LAN) upgrade, instructional walls.

     

    • Estimated Completion Date: 2020-2021 School Year

     

    Public Input Meetings

     

    Tuesday, February 5, 2019
    6:00 PM

     

    Roger M. Bryan Elementary School – Multi-Purpose Room
    8255 W. Katie Avenue
    Las Vegas, NV 89147

     

    Click here for postcard invitation.

  • Year Built: 1961

 

  • Number of Additional Classrooms: 18

 

  • Additional Scope of Work: Playground and parking modifications, replace cooling tower, boiler, chiller, HVAC (Heating, Ventilation, Air Conditioning) controls, fire alarm, security cameras, clock/intercom, LAN (local area network) upgrade, instructional walls, replace roof

 

  • Estimated Completion Date: 2020-2021 School Year

 

Public Input Meetings

 

Wednesday, February 13, 2019
6:00 PM

 

J.T. McWilliams Elementary School – Multi-Purpose Room
1315 Hiawatha Road
Las Vegas, NV 89108

 

Click here for postcard invitation.

  • Year Built: 2000

 

  • Number of Additional Classrooms: 14

 

  • Additional Scope of Work: Playground and parking modifications, replace cooling tower, boiler, chiller, HVAC (Heating, Ventilation, Air Conditioning) controls, fire alarm, security cameras, clock/intercom, LAN (local area network) upgrade, instructional walls, replace roof

 

  • Estimated Completion Date: 2020-2021 School Year

 

Public Input Meetings

 

Tuesday, March 5, 2019
6:00 PM

 

William K. Moore Elementary School – Multi-Purpose Room
491 North Lamb Boulevard
Las Vegas, NV 89110

 

Click here for postcard invitation.

  • Year Built: 1998

 

  • Number of Additional Classrooms: 22

 

  • Additional Scope of Work: Playground and parking modifications, replace cooling tower, boiler, chiller, HVAC (Heating, Ventilation, Air Conditioning) controls, fire alarm, clock/intercom, LAN (local area network) upgrade, instructional walls, replace asphalt

 

  • Estimated Completion Date: 2020-2021 School Year

 

Public Input Meetings

 

Wednesday, March 13, 2019
6:00 PM

 

Manuel J. Cortez Elementary School – Multi-Purpose Room
4245 E. Tonopah Avenue
Las Vegas, NV 89115

 

Click here for postcard invitation.

  • Year Built: 1976

 

  • Number of Additional Classrooms: 18

 

  • Additional Scope of Work: Playground and parking modifications, replace cooling tower, boiler, chiller, HVAC (Heating, Ventilation, Air Conditioning) controls, fire alarm, clock/intercom, LAN (local area network) upgrade, instructional walls, replace roof and asphalt

 

  • Estimated Completion Date: 2020-2021 School Year

 

Public Input Meetings

 

Monday, March 18, 2019
6:00 PM

 

C.H. Decker Elementary School – Multi-Purpose Room
3850 Redwood Street
Las Vegas, NV 89103

 

Click here for postcard invitation.